| Financial Assistance for Electrification of Remote
Unelectrified Census Villages
7. Pattern of Release of Funds
Release of the Central Financial Assistance for
approved projects will be made as per the following
pattern:-
- Initial release alongwith the sanction order
(provided Utilization Certificate (UC) for the
previous years’ releases have been received) - 50%
of the CFA
- Second installment on supply of equipment at site
- 20% of the CFA
- Final installment after commissioning and one
month of satisfactory operation - 30% of the CFA
Audited Statement of Expenditure (SOE) and UC should
be provided by the implementing agency along with a
certificate for electrification of the remote village
having been successfully carried out as per the Sanction
Order/DPR norms by the local administration at district
/ village level, after ascertaining from the
beneficiaries, before release of the final installment.
A confirmation from the State Power Department / State
Electricity Board the agency responsible for village
electrification, to the effect that the census villages
has been included in the list of electrified villages of
the State, would also be necessary before the final
installment is released.
|